Warm Springs K-8

Warm Springs K-8 Academy

Overview

Proposed Bond Projects

Health, Safety, & Security:

  • New Key/Access Control for Secure Building Access

Expand Vocational & Early Learning Programs:

  • New six-classroom addition

Project Updates

January 12 Update: 

WSK-8 is progressing nicely, roof is on, windows are installed, insulation is complete, sheetrock is being installed, rough in for electrical and mechanical is nearly complete.

 

October 24 Update: 

Framing has been underway for several weeks, trusses are being set and sheeted this week. Roofing will begin the first week of November followed by mechanical, electrical, fire sprinkler and HVAC rough-in.

Updates from September 25: 

Framing has started and will continue into October. Trusses will be set with a crane.

Updates from September 6:

Underground utilities are in, building slab is poured and ready for framing to begin. Framing should begin this week.

New parking lot which added 39 spaces is complete and ready for use.

jack_0000_Warm Springs Logo
  • Project Manager: Tiller's Schoolhouse Consulting
  • Architects: BBT Architects
  • Civil Engineer: DOWL
  • Structural Engineer: Walker Structural Engineering
  • Mechanical & Electrical Engineer: Morrison-Maierle Engineering
  • District Contact Information: Simon White, Director of Operations & Safety
  • General Information: bondprojects@509j.net
2022 2023 2024
J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A
Design
Construction
Owner Prep and Move-in

Project timelines and schedules are subject to change and will be updated when needed.