Madras High School

Madras High School

Overview

Proposed Bond Projects

Health, Safety, & Security:

  • New Key/Access Control for Secure Building Access

Expand Vocational & Early Learning Programs:

  • Updates to Existing Career & Technical Education Program Spaces

Repair & Update Aging School Buildings:

  • New Roof & Insulation
  • HVAC Upgrades
  • New Soccer Concession/Restroom Facility & Upgraded Field Lights

Project Updates

September 2023 

The Soccer field/Fieldhouse and CTE addition are complete and in use by students and staff.

40 HVAC units have arrived and installation begins week of 9/25. Roofing is complete with the exception of HVAC related work.

On September 13, our district held a ribbon cutting ceremony for the new soccer complex at MHS.

August 2023

We're thrilled to share the latest progress on our ongoing bond projects that are improving the health, safety, and security in our buildings. Here is an update on the work happening at Madras High School.

Soccer Complex Project:

Construction is well underway! The vision for the new and improved soccer complex is taking shape as new sod has been laid down, complemented by an irrigation system ensuring the field stays in great shape. The new lighting system is installed and this will help showcase varsity games and give more families the opportunity to see their student play.

The building's framework is up and the construction crew is now working on the roof, site work, and landscaping around the building.

Imagine a game the lights, a modern concession stand, restrooms, and locker rooms that will help elevate the soccer experience for our student-athletes and fans.

CTE Building Enhancement:

The work on our Career and Technical Education building is making remarkable progress. The framing, electrical, and plumbing work are nearing completion, and construction crews are working on adding sheetrock and exterior siding.

This work will allow our staff and students to have additional enclosed spaces for large projects and will allow them to work indoors shielded from the elements.

Roof:

More than 80% of the roofing is complete and the HVAC mechanical units are gradually arriving. This work will be ongoing through this Fall and Winter.

We appreciate your ongoing support and patience throughout this process. Together, we're improving on our spaces to allow students to flourish here. 

MHS Roof:

The roof replacement at MHS is currently in progress! As of May, the roof project is ahead of schedule with completion estimated by Fall 2023.

Soccer Complex Improvement Project:

Crews have installed lights at the MHS Soccer Field. In addition, new sod has been installed.
 
The walls for the Concession/Restroom Facility are also beginning to go up.
 

The foundation for the new soccer field house has been poured. Walls will begin to go up as soon as the materials arrive. Work on the field itself is underway. Old sod has been removed and the new irrigation system is being installed.

jack_0007_MHS Logo
  • Project Manager: Tiller's Schoolhouse Consulting
  • Architects: BLRB Architects
  • CMGC: Griffin Construction
  • Civil Engineer: HWA, Inc.
  • Structural Engineer: Walker Structural Engineering
  • Mechanical & Electrical Engineer: Morrison-Maierle Engineering
  • District Contact Information: Simon White, Director of Operations & Safety
  • General Information: bondprojects@509j.net
2022 2023 2024
J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A
Design
Construction
Owner Prep and Move-in

Project timelines and schedules are subject to change and will be updated when needed.