Buff Elementary

Buff Elementary

Overview

Proposed Bond Projects

Health, Safety, & Security:

  • New Key/Access Control for Secure Building Access

Repair & Update Aging School Buildings:

  • Roof Repairs
  • HVAC Upgrades

Project Updates

September 2023

Complete re-roof of south classroom wing was finished in August. More roofing work is scheduled for summer of 2024 along with HVAC and Controls work.

jack_0004_Buff Bear Logo

  • Project Manager: Tiller's Schoolhouse Consulting
  • District Contact Information: Simon White, Director of Operations & Safety
  • General Information: bondprojects@509j.net
2023 2024 2025
J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A
Design
Construction
Owner Prep and Move-in

Project timelines and schedules are subject to change and will be updated when needed.